Medco Energi is accelerating the development of its Sakakemang production sharing contract (PSC) in South Sumatra through an early production scheme, with a key Engineering, Procurement, and Construction (EPC) contract launched for the initial phase.

Sakakemang Development Plan

The development strategy involves an early production system targeted for 2027, to be followed by a full-field carbon capture and storage (CCS) development after 2028. This plan is based on a revised Plan of Development (POD) for the Kali Berau Dalam (KBD) field, which was initially approved for former operator Repsol. The POD is based on a natural gas capacity of 135 million cubic feet per day and includes a central processing facility (CPF) at the KBD-2X well pad, the drilling of two production wells, a one-kilometre pipeline to connect to the existing Transportasi Gas Indonesia (TGI) pipeline, and a 20-kilometre liquid CO2 pipeline to Medco's Grissik central gas plant. The KBD field's gas contains 26% CO2.

Phase 1A EPC Workscope

The EPC workscope for the Sakakemang Phase 1A early production project includes:

  • Wellsite facilities at the KBD well pad area.
  • A 22.5-kilometre, 16-inch diameter raw gas pipeline (clad with corrosion resistant alloy) from the KBD well location to the Grissik central gas plant on the adjacent Corridor PSC.
  • A 40-kilometre, four-inch diameter water injection pipeline from the Grissik plant to the North Sambar manifold, which will be constructed of non-metallic materials.

Contract Details and Prequalification

Prospective bidders for the Sakakemang EPC contract must register and collect prequalification documents by 30 March. An online clarification meeting is scheduled for 1 April, with the submission deadline for prequalification documentation set for 7 April 2026. This contract has a minimum local content (TKDN) requirement of 57%. Medco operates the Sakakemang PSC (expiring 2040) with a 45% stake and holds significant interests in the TGI pipeline (40%) and the adjacent Corridor block (70%).

Separate Rig Tender for Madura Offshore

In a separate procurement process, Medco is also seeking a jack-up drilling rig for its Madura Offshore working area offshore East Java. The estimated one-year contract, which includes one firm well, is scheduled to start between 1 September and 31 October this year. The prequalification deadline for this rig charter is 31 March. While the minimum TKDN for associated services is only 5%, Medco has strict bidding stipulations based on the rig's flag:

  • For an Indonesian-flagged unit: Bidders can be a domestic investment company (PMDN), a consortium, or a foreign company, provided a PMDN leads any consortium and contributes at least 30% of the contract value.
  • For a foreign-flagged unit: Bidders must be a PMDN company or a consortium including PMDN companies, with domestic companies performing a minimum of 10% of the contract value.
Producing assets on the Madura Offshore block include the Meliwis gas field, which started production in 2020.

29 March 2026



This material is an AI-assisted summary based on publicly available sources and may contain inaccuracies. For the original and full details, please refer to the source link. Based on materials by Amanda Battersby. All rights to the original text and images remain with their respective rights holders.

Our solutions

icon

nv.analysis

Decision support solution designed to identify potential well candidates for workovers and provide reliable geological and process data

  • icon

    Cloud / on-premise

  • icon

    Pre-project survey

  • icon

    Proof of Concept

  • icon

    24/7 technical support

icon

nv.planning

Decision support solution for integrated planning of onshore and offshore upstream operations

  • icon

    Cloud / on-premise

  • icon

    Pre-project survey

  • icon

    Proof of Concept

  • icon

    24/7 technical support

icon

nv.ID

Data storage solution for managing downhole equipment lifecycle

  • icon

    Cloud / on-premise

  • icon

    Pre-project survey

  • icon

    Proof of Concept

  • icon

    24/7 technical support