News Digest (www.upstreamonline.com)
Sunda Energy and Finder Energy have formed a collaboration to secure a drilling rig for their respective offshore Timor-Leste campaigns, aiming to make the projects more attractive to contractors by combining operations.
Drilling Campaigns and Rig Requirements
Sunda Energy plans to drill the Chuditch-2 appraisal well on the TL-SO-19-16 PSC, while Finder Energy intends to drill at least three wells for its Kuda Tasi and Jahal (KTJ) fields development, targeting a final investment decision by mid-year. Finder requires a semi-submersible rig for its KTJ wells in approximately 400 metres of water. Although Chuditch-2 is in shallower water (~65 metres) and could use a jack-up, the plan now aligns with using a semi-submersible rig, similar to the original Chuditch-1 well drilled by Shell.
Schedule Delay and Challenging Market
Sunda now anticipates Chuditch-2 will not start until "as early as possible in 2027," a delay from the previously scheduled mid-2026. The company cited a "challenging" market for securing a rig, primarily due to the well's short expected duration of 30 to 45 days with no immediate follow-up work planned. In response to this delay, SundaGas has applied to Timor-Leste's regulator ANP to extend its Production Sharing Contract, which is set to expire on 18 June.
Collaboration Benefits and Agreement
The companies have entered a Letter of Intent (LoI) to collaborate on a combined offshore drilling campaign. Key aspects of the collaboration include:
- Sharing a semi-submersible rig, with Finder already advanced in securing a suitable unit.
- Aligning contracts for other materials and services.
- Coordinating project management and providing mutual support for their drilling programmes.
This partnership creates a combined operational duration of nearly 200 days, which Sunda states is "a far more attractive proposition for contractors." The LoI will terminate upon execution of a formal rig sharing agreement or on 31 October, unless extended.
Operational Adjustments
Using a different rig type for Chuditch-2 will require minor amendments to the well engineering design, and this work is scheduled to commence soon.
9 April 2026
This material is an AI-assisted summary based on publicly available sources and may contain inaccuracies. For the original and full details, please refer to the source link. Based on materials by Amanda Battersby. All rights to the original text and images remain with their respective rights holders.