Running a forecast calculation (base case)
To start a forecast calculation, do the following:
1.Go to the Model calculation menu in the upper-right corner of the screen.
2.On the Forecast calculation tab, select the No optimization option and click Calculate.
| Important When running a forecast for wells with linked material balance models, reservoir pressure (and the other parameters) on the first forecast step come not according to the date specified in nv.AIM PIPE, but according to the first forecast step specified in the MBAL reservoir model. |